GRDA Coal Dumper Replacement

Energy & Power,

GRDA Coal Dumper Replacement

To date, Williams Construction has successfully completed four coal dumper replacement projects. The team at Williams has found a niche in completing critical coal dumper projects. We are able to utilize the expertise of our project managers, safety team, and highly skilled field team to ensure that these jobs are done correctly, safely and timely.

Williams Construction removed the current coal dumper and replaced it with a newly assembled coal dumper and installed an HPU system in 18 days. This project was completed ahead of schedule during a shutdown.

Key Stats:

  • 12000 Man hours
  • Zero hours of lost time due to safety incidents