Cabot EPA Compliant Upgrades

Chemical,

Scheduled during an plant annual shutdown, this was a 12-week project that Williams Construction collaborated on as the general contractor with a regional engineering firm. This project consisted of equipment foundations, several areas of structural steel repairs and replacements and installation of new IP fans. The overall project scope consisted of several upgrades and additions of new components to comply with new EPA regulations.

Key Stats:

  • Zero hours of lost time due to safety incidents