This 10 week project featured the drilling of piers ranging from 48” to 72” in diameter and 30′ deep, the installation of 71 concrete pipe trestles and the installation of all necessary concrete columns topped with concrete beams. Concrete columns ranged from 14’-22’. Concrete beams ranged from 8’-11’ in size.
Key Stats:
21000 man hours
Zero hours of lost time due to safety incidents
We use cookies on our website to enhance your user experience and to analyze site usage so we can further improve our website and marketing. By clicking "Accept" you agree to our use of cookies. Continuing without accepting cookies will limit the functionality of the site. To learn more about how we use cookies, view our Privacy Policy.AcceptDecline