Paint Booth Installation

04/07/2020

This six-month project consisted of 9,652 labor-hours from the Williams team, all recorded safe hours. The project consisted of demolition of the existing paint booth. Placement of new footings for structural steel going through the roof deck, installation of platform rooftop air-handling units. The electrical and mechanical were also relocated, which included fire alarm protection and the installation of a new two-hour protective firewall.

Triumph Aerostructures G650 Rearrangement

05/16/2018

Williams relocated tooling fixtures and reconfigured work platforms associated with the Gulfstream G650 Program. The team also installed utility distribution structures to support compressed air and electrical services. Key Stats: 1000 man hours Zero hours of lost time due to safety incidents

Spirit AeroSystems Skin Mill Foundation

05/16/2018

This project involved the installation of a foundation system for a 250’-0” x 30’-0” skin mill in an existing, occupied building. The foundation system was five to seven feet thick with embedded wide flange beams at 2’-0” on center. Along each side and down the length of the foundation were conveyor trenches. These trenches were poured monolithic with the foundation. The pour was 720 cubic yards placed and finished in 14...