This project featured the installation of all concrete foundations for substation buss duct and breakers, containment pits with piers for 2 new transformers, 60” piers for lightning protection rods, grounding grid and high security fence. Key Stats: 13,700 Man Hours Zero hours of lost time due to safety incidents
For this project, Williams Construction converted an existing refining building to a state of the art lubrication research facility. All activities for this project were coordinated with the client through 10 phases, to ensure the research building could remain occupied and functioning throughout the entire project. The Williams Construction Team retrofitted the building to accept the HVAC upgrade by demolishing the existing air handler and structural steel platform to allow for...
This project involved the break down and relocation of all production equipment and associated structures from Containment Solutions’ existing facility in Conroe, Texas to their new facility in Tulsa, Oklahoma. The Williams Construction Team successfully disassembled the entire plant, moved parts and reassembled structures and equipment to working condition at new location. 10700 Man hours Zero hours of lost time due to safety incidents