During this project, Williams Construction replaced eroded and corroded steel members in an elevated structure during facility operation. All work was performed in an operating facility with no impact to the continuous operation of the plant. Key Stats: 6500 man hours Zero hours of lost time due to safety incidents
Scheduled during an plant annual shutdown, this was a 12-week project that Williams Construction collaborated on as the general contractor with a regional engineering firm. This project consisted of equipment foundations, several areas of structural steel repairs and replacements and installation of new IP fans. The overall project scope consisted of several upgrades and additions of new components to comply with new EPA regulations. Key Stats: Zero hours of lost time...
During this 12-week project, Williams Construction performed upgrades and replacements to an aging coal bin and the surrounding structure. The project scope included lifting out the existing bin, modification of the existing structural steel to be able to fit and hold new 45-ton capacity material bin, and replacement of all the surrounding structures including access platforms on several levels. During this project, the Williams Construction team collaborates with facilities partners to...