Interplastics

04/14/2026

Kerr Dam

04/14/2026

Gold Bond

04/14/2026

Railcar Indexer and Ring Dryer Access Platform

04/07/2020

This capital enhancement project included the modification of existing concrete, the installation of concrete piers, along with the fabrication and installation of structural steel supports. The Ring Dryer Access Platform included the fabrication and installation of equipment access platforms for an existing structure.

Paint Booth Installation

04/07/2020

This six-month project consisted of 9,652 labor-hours from the Williams team, all recorded safe hours. The project consisted of demolition of the existing paint booth. Placement of new footings for structural steel going through the roof deck, installation of platform rooftop air-handling units. The electrical and mechanical were also relocated, which included fire alarm protection and the installation of a new two-hour protective firewall.